THE SCOPE:
Construction of a 900,000 Barrel Tank Farm and Adjoining Facilities, Phoenix Industrial Completed all Civil, Structural, Piping, Insulation, Scaffolding, Mechanical Installation, and Site Wide Services.
TYPE OF PROJECT:
Terminal
MANAGEMENT OF SUB-CONTRACTORS:
As the General Contractor, Phoenix Industrial managed more than 25 third party subcontractors for the execution of the scope. This included every type from Earthworks, to Heavy Lift and Non Destructive Testing
MANPOWER REQUIRED:
More than 660,000 Man hours over 18 Months
SAFETY RECORD:
Completed with Zero Lost Time Incidents